2003
Maine Wastewater Salary Survey as conducted by the Maine Wastewater Control
Association
2003 Maine
Wastewater Rate Survey conducted by the Maine Rural
Water Association
Maine DEP Monthly
O & M Newsletter
Maine and WEF's
Operation Forum
Penobscot Watershed and Development of a TMDL
EPA Binational Toxics
Strategy
Maine Rural Water
Association
Maine Wastewater
Operator Certification
Guide
Maine Is Technology
Newsletter
Maine
Wastewater Control Association
Maine
Wastewater Engineering
Firms
| |
In 1990, the Town of Thomaston initiated a wastewater system improvement
program, the essence of which was to improve the water quality of the St.
George River by the elimination of combined sewer overfIows (CSOs) in the
sewer system and to improve the compliance record of the treatment
facility. The Town began an aggressive sewer replacement program in an
effort to eliminate the CSOs. The Town retained Wright-Pierce to conduct
an evaluation of the existing treatment plant to determine the scope of
work necessary to upgrade the plant to meet the current and future needs
of the Town.
In 1992, the Town determined it was in its best interest to
construct a completely new treatment facility. The Town and the Maine
Department of Environmental Protection (DEP) agreed to evaluate
alternatives that would eliminate the existing discharge to the St. George
River. The St. George River is a very productive shellfish area, and by
eliminating Thomaston's wastewater discharge, much of the area previously
closed to shellfishing could be opened. It was determined that complete
elimination of the river discharge was not economically feasible.
The Town and the DEP worked together to develop an
alternative that fit within the available funding and would utilize land
application of treated effluent for as much of the year as possible (May
through October) and discharge to the river only in the months of January,
February and March when much of the river is typically frozen and less
accessible for shellfishing. The total area with suitable soils for land
application was limited at the proposed treatment site, however those
soils present would allow a spray application rate of three inches per
week (twice the typical rate in Maine) which made the alternative
feasible. This alternative would ultimately allow those areas of the St.
George River currently closed to shellfishing to be opened for
approximately nine months each year.
By the end of 1997, the new pumping stations began transporting
Thomaston's wastewater to the new treatment facility culminating a 7-year
process to upgrade their wastewater collection system and replace their
30-year old treatment plant.
New Facilities
In 1991, the Town began a sewer replacement program to reduce
the amount of non-sanitary (stormwater and groundwater) flows in their
sanitary sewer system. By the end of 1997, the Town had replaced
approximately 36,500 linear feet of gravity sewer pipe and associated
sewer services to each building, and installed five new pump stations with
approximately 7,100 linear feet of force main pipe. Through this effort,
the Town has eliminated all of its CSOs and no longer discharges untreated
wastewater to the St. George River during rainstorms.
The new wastewater treatment facility also went on-line at
the end of 1997. The treatment facility consists of three aerated
facultative treatment lagoons constructed in series with a total capacity
of 21 million gallons. The treatment lagoons are followed by a storage
lagoon with a capacity of 36 million gallons. The facility is designed to
treat an average daily flow of 427,000 gallons per day. Aeration is
provided to the treatment lagoons via three blowers, air distribution
piping, and 98 fine-bubble tubular membrane diffuser assemblies.
The treated effluent from the lagoons is disposed of in one
of two ways. In January, February and March the effluent is disinfected
with sodium hypochlorite and discharged by gravity through 7, 100 linear
feet of pipe to the St. George River via the outfall pipe at the old
treatment plant. From mid may through October, the effluent is land
applied by a spray irrigation system consisting of two 75 Hp spray pumps,
approximately 26,000 linear feet of distribution piping, and 130 spray
nozzles. The land application area is divided into five fields, each
consisting of approximately ten acres. The
effluent is
applied to one field at a time, with each field being used one day each
week. Between the river discharge period and the land application season,
the treatment lagoon effluent is stored in the storage lagoon. The 78-foot
x 40-foot operations building at the treatment facility includes a control
room, laboratory, blower room, chemical room, pump room and a garage.
Funding
The total cost of the project, which began in 1991, was $12.2
million, including construction, land acquisition, administration, and
technical services. The total construction cost was approximately $8.5
million. The project was funded by state and federal grants and loans from
the Department of Environmental Protection (DEP), the Rural Utility
Service (RUS), and the Maine Municipal Bond Bank (MMBB) as summarized
below.
Maine DEP: |
Grants $5.1-million |
Loans $2.35-million |
RUS: |
Grants $1.26-million |
Loans $2.74-million |
MMBB: |
Loan $0.75-million |
|
Lagoon
Specifications
Lagoons |
No.1 |
No.2 |
No. 3 |
Storage |
Volume |
10.5 MG |
5.25 MG |
5.25 MG |
36 MG |
Lagoon Size |
600' x 240' x 15' |
350' x 240' x 15' |
350' x 240' 15' |
960' x 370' x 20' |
Lagoon Acreage |
3.38 acres |
3.3 acres |
3.3 acres |
8.2 acres |
Aeration |
Fine Bubble |
Fine Bubble |
Fine Bubble |
None |
Number of Units |
70 |
16 |
12 |
None |
Comments: Lagoon acreage including berms is 25 or 1,089,000 square feet.
Facility has (3) motor blower sets, all 25 horsepower driving 350 SCFM
positive displacement blowers. One has an Allen Bradley VFD. Aeration system
manufacturer is Environmental Dynamics, Inc and diffuser model is the
FlexAir.
|
System Information
Design Flow |
0.430 MGD |
Actual Flow |
0.270 MGD |
Discharge To |
Winter-St. George River; Summer to Land Application |
Year Built |
1997 |
Design Engineers |
Wright-Pierce |
Septage Received |
No |
Collector System |
11
miles of gravity, 355 manholes, 5 pump stations |
Staff Size |
Two
Full Time, 1 Part Time |
Number of Users |
800
Services plus Maine State Prison |
Comments |
Seasonal (Jan.-Mar.) river discharge and land application May-Oct., to a 50
acre spray area. The
Thomaston Town Forest Trail System, a section of the Georges
Highland Path, begins at the treatment facility. |
Process Flow Schematic
click on schematic for larger size
Basic Design Data
Ship Street Pump Station
A. Influent Pumps
Type: Submersible
Number of Pumps: 2
Capacity: 1700 gpm @ 137 feet TDH
Motor: 100 Hp
B. Mechanical Bar Screen
Bar Spacing: 1/2 inch
Drive Motor: 11/2 Hp
Wastewater Treatment
Facility
A. Treatment Lagoons
Type: Aerated-Facultative
Design Average Daily Flow: 0.427 mgd
Influent BOD: 885 lbs/day
Number of Cells: 3
Total Lagoon Volume: 21 million gallons
Liquid Depth: 15 feet (max), 12 feet (min)
B. Aeration Equipment
Blowers
Type: Positive Displacement
Number: 3
Capacity: 3 70 SCFM each
Drive Motor: 25 Hp
Aerators
Type: Fine-Bubble Tube Membrane
C. Storage Lagoon
Number of Cells: I
Storage Period: April 1 - May 15, Nov I - Dec 31
Total Lagoon Volume: 36 million gallons
Maximum Liquid Depth: 20 feet
Aeration System: None
D. Disinfection
Chemical Used: Sodium Hypochlorite
Application Points: Effluent Piping / Operations Building Disinfection
Period: Jan I - March 31
Chemical Storage: 2-550 gallon tanks
E. Spray Irrigation
Typical Spray Period: May 15 - Oct 31 (24 weeks) Number of Fields: 5
Size of Fields: 10.2 acres each
Application Rate: 3 inches/week
Spray Pumps
Type: Horizontal Split Case
Number: 2
Capacity: 1050 - 1350 gallons/minute
Operator Name |
John Fancy |
Facility Address |
Dover Road |
|
Thomaston, Maine 04861-0299 |
Telephone |
(207) 354 - 2131 |
Fax |
(207) 876 - 2137 |
Back to Lagoons in Maine
|